Children's Building Renovation - Week #11. This week the porch was completed and new exterior doors were installed. The check-in cabinets for both floors were also started. The Tech Team is busy running wire and preparing computers to be installed. Valances are being sewn and the displays are in the hallway. The child care office has counter tops. Part of the basement for phase 2 has been vacated. Ceilings, lights and HVAC are getting attention. March 30, we begin moving back into the children's building. Sunday, April 1 preschoolers will have Bible study in their new classrooms. The child care center opens on April 2 in renovated space. Phase 2 area in the basement will be completely vacated by April 1. Please do not enter any space marked off with yellow tape.